Mound Laboratory

Location

500 Vantage Point

Miamisburg, Ohio

In 1943, the Manhattan Engineer District began the Dayton Project to investigate the chemistry and metallurgy of polonium. From 1943 to 1948, this work was performed at several locations throughout Dayton, Ohio, all of which were too small to perform the mission. The Mound Plant was constructed in 1947 in Miamisburg, Ohio, to replace these earlier work locations. This plant was first occupied in May 1948 and became operational in February 1949.
The facilities’ first mission was to manufacture polonium-beryllium initiators for atomic weapons. As part of this process, the site extracted polonium-210 from irradiated bismuth slugs and machined beryllium parts. Mound stopped producing initiators after the Pinellas Plant in Florida began producing accelerator-type neutron generators in 1957. In 1954, Mound began developing and producing weapons components containing tritium, and in 1969, the plant began recovering and purifying tritium from dismantled nuclear weapons. During the 1950s and 1960s the Mound Plant also developed and produced a variety of nonnuclear weapons components including detonators, cable assemblies, firing sets, ferroelectric transducers, and explosive timers. In 1995, Mound discontinued weapons components production.
The non-weapons work performed at the Mound Plant included the development and manufacture of radioisotope thermal generators; radioactive waste decontamination research; investigation of the properties of uranium, protactinium-231, and plutonium-239; and the separation of stable isotopes and noble gases.
Throughout the course of its operations, the potential for beryllium exposure existed at this site, due to beryllium use, residual contamination, and decontamination activities.
The non-weapons work performed at the Mound Plant included the development and manufacture of radioisotope thermal generators; radioactive waste decontamination research; investigation of the properties of uranium, protactinium-231, and plutonium-239; and the separation of stable isotopes and noble gases.
Throughout the course of its operations, the potential for beryllium exposure existed at this site, due to beryllium use, residual contamination, and decontamination activities.

Alternative Names

  • Mound
  • Monsanto Research Corporation
  • Miamisburg Environmental Management Project
  • MEMP
  • Mound Plant
  • Miamisburg Closure Project
  • The Mound
  • Unit IV

Type of Facility

  • Department of Energy

Covered by EEOICPA

  • B and Part E

EEOICPA Covered Years

  • 1947-Present

Contractors

  • 2006-Present S.M. Stoller Corporation
  • 2006-2010 Accelerated Remediation Company
  • 2003-2006 CH2M Hill
  • 1997-2002 BWX Technologies
  • 1988-1997 EG&G Mound Applied Technologies
  • 1947-1988 Monsanto Chemical Company

Contract Numbers

  • AC04-76DP00053
  • EY-76-C-04-0053
  • AT(33-1)-GEN-53
  • AC24-88DP43495
  • AC07-76ID01570
  • AC08-89NV10630
  • DE-AC04-88DP43495
  • EY-76-C-04-3533
  • EY-76-C-04-0789
  • EY-76-C-04-0063
  • E(33-1)-GEN-53
  • AT-33-1-GEH-53, Modification No 2
  • AC04-92AL73000
  • AC04-88DP43495
  • AC04-76DR00789
  • AC04-76-DP00053
  • AT-33-1-Gen-53 Appendix D

DOE

DOL

EPA

NIOSH

  • FAQs About Your Case
  • Advisory Board on Radiation and Worker Health
  • NIOSH Case Statistics
  • Special Exposure Cohort Status Table
    • Petition 090, 091: “Employees of the Department of Energy (DOE), its predecessor agencies, and DOE contractors or subcontractors who worked in any areas at the Mound Plant site from October 1, 1949 through February 28, 1959 for a number of work days aggregating at least 250 work days or in combination with work days within the parameters established for one or more other classes of employees in the Special Exposure Cohort.”
    • Petition 171: “All employees of the Department of Energy (DOE), its predecessor agencies, and its contractors and subcontractors who had at least one tritium bioassay sample and worked at the Mound Plant in Miamisburg, Ohio from March 1, 1959 through March 5, 1980, for a number of work days aggregating at least 250 work days, occurring either solely under this employment, or in combination with work days within the parameters established for one or more other classes of employees in the Special Exposure Cohort.”
    • Petition 207: “All employees of the Department of Energy, its predecessor agencies, and their contractors and subcontractors who worked at the Mound Plant in Miamisburg, Ohio, from September 1, 1972, through December 31, 1972, or from January 1, 1975, through December 31, 1976, for a number of work days aggregating at least 250 work days, occurring either solely under this employment or in combination with work days within the parameters established for one or more other classes of employees in the Special Exposure Cohort.”
  • Work Site Information

Other Resources

related posts

Vulcan Tool

Vulcan Tool

Location 730 Lorain Avenue Dayton, Ohio At the request of National Lead Company of Ohio (Fernald), Vulcan Tool Company conducted experiments involving the cutting of normal uranium slugs and tubes on a Brehm cutter in October 1959. Type of Facility Atomic Weapons...

read more
Tocco Induction Heating

Tocco Induction Heating

Location 3800 Harvard Avenue Cleveland, OhioTocco had a contract with National Lead of Ohio (Fernald) to develop induction heating coil equipment for heating uranium fuel cores. Tocco performed operational tests of these units at its Ohio facility, which took place...

read more
Tech-Art

Tech-Art

Location Milford, OhioIn 1952, National Lead Company of Ohio (Fernald) used Tech-Art to grind inserts as part of a study of Firth Sterling HF carbide profile inserts in conjunction with the machining development program. Additional documentation shows that Tech-Art...

read more